Millrace Crossing opened to traffic this week, three weeks ahead of the contract date. The 320-metre cable-stayed bridge replaces a 1960s crossing and adds a protected cycle lane and a wide footpath.
Project facts
| Item | Figure |
|---|---|
| Main span | 180 m |
| Stay cables | 48 |
| Concrete | 21,000 m³ |
| Steel | 3,600 t |
| Peak workforce | 190 |
The towers were slip-formed in continuous pours, and the deck segments were cast on the riverbank and lifted into place, which kept most of the work out of the water during the fish migration season.
Keeping the work out of the water was the hardest constraint and the best decision we made.
Bridge project manager
Our thanks to the city's engineers, the river authority and the residents of the east bank.
