A family-owned logistics company with three depots ran its dispatch, accounts and file shares on fourteen servers in a back office. The hardware was out of warranty and the last full restore test was a memory.
14 → 3
servers after consolidation
31%
lower monthly running cost
0
missed deliveries during the move
The approach
- Weeks 1–2: inventory, dependency mapping and a tested backup of everything.
- Weeks 3–6: file shares and email first, because they are easiest to roll back.
- Weeks 7–11: accounts and dispatch, moved over two Sunday nights.
- Week 12: old servers wiped, recycled and certificates issued.

Monday after the dispatch move, the drivers didn’t notice anything. That was the whole point.
Operations director, client
The company now runs on Cloudline’s Professional plan, with monthly cost reviews that have found further savings each quarter.